New extension in Great Barr, Birmingham.
  |
Demolishing of existing lean-to, preparation of existing
ground and new foundations. |
 |
Laying of new foundations. |
   |
New brickwork to damp course. |
  |
Brickwork to window height. |
    |
Internal block work, windows and door way openings. |
      |
Installation of supporting steel work and lintels. |
  |
Scaffolding for first floor brickwork construction. |
    |
Installation of first floor timber joists. |
  |
First floor brickwork. |
   |
First floor brickwork to roof height. |
    |
First floor brickwork complete and ready for roof timbers. |
    |
Construction of roof timbers and ceiling joists. |
    |
New roof construction taking shape. |
    |
Felt, battening and laying of roof tiles. |
    |
Outer shell and roof complete. |
  |
New upvc doors and windows fitted. |
  |
New extension complete. |
New extension in Coleshill, Warkwickshire
    |
Damp course brickwork to front, side and rear. |
    |
Brickwork upto first floor level with ceiling/floor joists
fixed. |
    |
Inner block work being finish to first floor level. |
    |
Roof timbers and internal stud work. |
     |
Roof timbers fixed and roof tiled. New upvc windows
being fitted. |
    |
A view of the side and rear elevations. |
   |
External work near completion. |
     |
Boarding out and plastering the internal walls |
  |
Installation of the central heating system. |
|